PE water supply pipeline construction process flow
PE water supply pipeline construction process flow: 1. Mechanical excavation to the base 20cm 2. Manual excavation to the base 3. The acceptance of the base slot is qualified 4. Foundation Construction 5. Down tube installation 6. Interface 7. Install valves and fire hydrants 8. Masonry inspection well 9. Pipeline pressure test 10. Flushing and disinfection 11. Pipeline backfill